Project Name

Cote Village - 9% Townhomes

This project has been completed and no further work is being done.
Project Parcels

1801054000

30 Regis RD
Owner:
Other
56,913sqft

No photos uploaded (yet!)

Neighborhood
Mattapan
Councilor
Arroyo
Units Total
24
Income-Restricted Units
24
Property Size
56,913 sq/ft

Developer

Planning Office for Urban Affairs POUA

Project Goals

The Cote Village site is comprised of four vacant parcels on city-owned land totaling 113,695 square feet located at the corner of Cummins Highway and Regis Road outside of Mattapan Square is planned for mixed income housing and commercial development.

The development team consisting of Caribbean Integration Community Development, Planning Office for Urban Affairs was designated as the development team.

The proposal which was selected by the community and DND in response to a Request for Proposals, consists of the creation of 76 rental apartments in two projects. One building will contain 52 units, and there will be an additional 24 units in townhome style buildings. Of the 76 units, 8 will be rented as market-rate units while the remaining 68 will be income-restricted affordable units. Of the 76 units 17 will be one-bedrooms, 47 will be two-bedrooms and 12 will be three-bedrooms.

The Cote Village project received Article 80 and 121A approval from the Boston Planning and Development Agency.

The project started construction but is currently paused due to COVID 19.

Timeline

Spring 2013

Community Feedback

We’re meeting with community members to gather feedback on plans for the site.

Summer 2014

Developer Selection

We’ll release a Request for Proposals and select a developer for this site.

Jun 30, 2014

Request for Proposals (RFP) Opened for Bidding

Spring 2015

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Winter 2019

Under Construction

Construction is underway. For further information on road closures and parking impact, contact the Project Manager.

Fall 2021

Project Complete

This project is ready for use.