Project Name
Mildred Hailey-Building 2
Project Parcels
Neighborhood
Jamaica Plain
Councilor
Weber
Units Total
65
Income-Restricted Units
65
Property Size
49,319 sq/ft
Developer
Jamaica Plain Neighborhood Development Corporation JPNDC
Project Goals
Mildred Hailey Building 2 will be developed by JPNDC. The proposed project includes demolition and abatement of two existing buildings to create a new 6-story, 100% affordable 65-unit building.
Timeline
Winter 2023
Funding awarded
Mayor’s Office of Housing approved funding for this project.
Winter 2023
City Planning
City Planning
This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.
Under Construction
Under Construction
Predicted Date: Spring 2025
Project Complete
Project Complete
Predicted Date: Fall 2026