city_hall

Mareegaha rasmiga ah waxay isticmaalaan .boston.gov

Mareegta .boston.gov waxay ka tirsan tahay urur dawladeed oo rasmi ah oo ku yaalla City of Boston.

lock

Mareegaha .gov ee sugan waxay isticmaalaan HTTPS

Quful ama https:// waxay ka dhigan tahay inaad si ammaan ah ugu xirmatay mareegta .gov. La wadaag macluumaadka xasaasiga ah oo kaliya mareegaha rasmiga ah ee sugan.

Boston.gov Search

Get direct answers to your questions about City of Boston services, programs, and information. While we strive for accuracy by sourcing directly from Boston.gov, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer.

Su'aalo? Nagala soo xiriir: digital@boston.gov.

Dooro nooca raadinta

William Felton 'Bill' Russell Bridge

Public Works is designing a replacement for the bridge in Charlestown. MassDOT will construct the new bridge.

Su'aalo ma qabtaa? La xiriir:

Wajiga Mashruuca

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete

Macluumaadka Mashruuca

Location
North Washington Street Bridge Charlestown 02129
See all
Sannadka La Dhammaystiray
2025
Primary Project Type
Streets

The new bridge will complement the Zakim Bunker Hill Bridge next door. The new bridge will be walkable, multi-modal, green, and sustainable. Everyone will be able to safely use the bridge. That includes pedestrians, cyclists, and motorists.

The design calls for:
  • wider sidewalks
  • gathering places
  • innovative accent lighting
  • protected bicycle facilities, and
  • smoother walking surfaces to support the Freedom Trail.

Timeline

Timeline
  • July 16, 2017: Plan Specification and Estimate Submission (Final)
  • September 16, 2017: Advertised for Bidding
  • February 27, 2018: Bids Opened
  • August 18, 2018: “Notice to Proceed” Provided to JW White
  • 2019/2020: Temporary bridge constructed
  • July 18, 2020: Traffic switched to temporary bridge
  • December 9, 2023: Traffic switched to permanent bridge
  • October 21, 2024: Ceremony celebrating the Bridge Renamed William Felton “Bill” Russell Bridge
  • Summer 2025: Anticipate all lanes on permanent bridge to be open